Framing crew is fast! They framed the garage and the floor of second floor in a single day.
Friday, December 16, 2022
Progress update #2
Interior Framing is going up.
Upstairs interior walls mostly there. Rough in plumbing and electrical has started.
Progress update #1
Permits issued finally! Took ages and answering a bunch of dumb questions that could have been asked from the start. Oh well, they are issued now.
Full speed ahead now. Sewer connect is schedule for Dec 1-2, foundation work starts on Dec 4th.
Started with lots of demo. Found an unfortunate number of surprises.
Some poorly supported ceiling josts, required a beam addition.
The walls were some crazy combo of fiberboard covereed by plaster covered by drywall.
This concealed multiple roof leaks around the house, so lucky us, new roof is now part of the job.
various other changes due to things not as expected.
Got a bunch of demo photos for this update.
#26 Master bedroom and closet
Master is good to go now as well, again except for a few handles..... I ordered way short. It was a lot harder cutting those angled lines ...
-
Progress update #1 Permits issued finally! Took ages and answering a bunch of dumb questions that could have been asked from the start. O...